Projects
We’ve Done The Hard Part
So You Don’t Have To

Route, Constructability, ITB
Some of the challenges:
- Minimizing equipment handling.
- Defining equipment installation sequence (120T~470T equipment)
- Scope of Work development
Solution:
- Proposed heavy haul route.
- Redesign steel structure to enable usage of lift frame.
- ITB, RFQ and Technical Scoring Matrix

HL/HH Planning & Budgeting
Some of the challenges:
- Planning and budget analysis of the structure to determine HL/HH strategy. Transport and install fully or partially assembled. (~ 135T)
Solution:
- Performed scenario analysis integrated with client team.

Levee Crossing
Some of the challenges:
- Delivery of 700T vessel near Mississippi River jobsite.
Solution:
- Levee Crossing. Provided all engineering and permit coordination.

HL/HH Management
Some of the challenges:
- Onsite management of all HL/HH and barging activities.
Solution:
- Provided fulltime HL/HH Manager along with inhouse engineering backup. Daily reporting to client with monthly cost savings overviews.

Turnaround Support
Some of the challenges:
- Defining TAR crane requirements, Maximize efficiency
Solution:
- Defining TAR HL requirements, including crane sizes, placement, crane pads.
- Overseeing and coordination of all HL activities during TAR

Engineering Solutions
Some of the challenges:
- Provide a solution to exchange 200 reformer tiles. Eliminate cumbersome individual bull-rigging scenarios.
- Minimize turnaround critical path duration.
Solution:
- Track design with multiple gantries.

Engineering Solutions
Some of the challenges:
- Provide a lightweight lift system in congested site area.
- Avoid removal of site obstructions.
Solution:
- Designed and fabricated a lightweight aluminum modular gantry.

Engineering Solutions
Some of the challenges:
- Providing safe and quick access to perform full internal Sphere Inspections.
- Minimize turnaround critical path duration.
Solution:
- Designed and fabricated an aluminum rotating access system (reduced installation from 30 days to 4 days)

Turnaround Support
Some of the challenges:
- Minimize 65T condenser change out critical path duration.
- Minimize removal of obstructions.
Solution:
- Proposed unique jack-and-slide solution in combination with HH/HL.